Project Name | Four Laning of Dwarka (Kuranga) – Khambaliya – Devariya Section from Km. 203/500 to 176/500 and from Km. 171/800 to Km. 125/000 (designed length 71.890 km) of NH-151A in the State of Gujarat under Bharatmala Project on Hybrid Annuity Mode (Package - I) |
NH No. (New/old) | NH-151A (Package-1) |
---|
Scheme/Phase | Construction Development Phase Bharatmala |
---|
Mode of the Execution (HAM) | Hybrid (Annuity) Mode |
---|
No. of Lanes/Configuration | Four Laning |
---|
Length of the Project (in Km) | 71.820 Km (Existing from 203+500 to 176+500 and Existing from 171800 to 125+000 also SH-25 4.6 Km from 125+000 to 130+000) |
---|
Contract Price (in Cr) | 1101.00 Cr. |
---|
Length of Service Road (in Km) | 2 x 9.090Km |
---|
Length of Drain (in Km) | 32.885 L-Km |
---|
No. of ROB | 01 No (0+527) |
---|
No. of Major Bridges | 04 No Reconstruction |
---|
No. of Minor Bridges | 16 No Reconstruction
04 No Widening & Rehabilitation
|
---|
No. of Toll Plazas | 01 No (61+400) |
---|
No. of Vehicular Underpass | 06 No New Construction |
---|
No. of Box Culvert | 24 No Reconstruction
11 No Widening & Rehabilitation
|
---|
No. of Hume Pipe Culvert | 69 No New construction
16 No Widening & Rehabilitation
|
---|
No. of Major Junction | Nil |
---|
No. of Minor Junction | 55 No (T type: 34, X type: 20, Y type: 1) |
---|
No. of Bus Bays | 50 No |
---|
Contractor Name (SPV & Parent Company) | GR Dwarka Devariya Highway Private Limited (GDDHPL) & G R Infraprojects Ltd. |
---|
Date of Award (LOA Date) | 08th March 2019 |
---|
Agreement Signing Date | 22nd May 2019 |
---|
Appointed Date | 08th February 2020 |
---|
Construction Period (in Days) | 912 Days |
---|
Scheduled Date of Completion | 07th August 2022 |
---|
Extension of Time (EOT) | 180 Days (approved from Authority) |
---|
Revised Schedule Date of Completion | 03rd February 2023 |
---|
Independent Engineer | LEA Associate South Asia Pvt. Ltd (LASA |
---|
Operation & Maintenance Period | 15 Years from the Commercial Operation Date |
---|
Independent Engineer Mobilization Date | 20th November 2019 |
---|
Independent Engineer | LEA Associate South Asia Pvt. Ltd (LASA) |
---|
Authority Name | National Highways Authority of India, PIU-Rajkot |
---|