Project Milestones

Project Milestones

Project
Milestone
Description
(Days from
Appointed
Date )
Scheduled
Date
Planned Actual Current
Physical Status
Physical
Progress (%)
Description
(Date after
EOT-2)
Scheduled
Date (After
EOT-2)
Physical
Progress (%)
Revised Date
Milestone I225 Days19th September 202020%405 Days18th March 202122.309%03-03-2021
Milestone II450 Days02nd May 202135%630 Days29th October 202135.66%09-06-2021
Milestone III675 Days13th December 202175%855 Days11th June 2022
Scheduled Completion912 Days07th August 2022100%1092 Days03rd February 2023