Project Milestone |
Description (Days from Appointed Date ) |
Scheduled Date |
Planned | Actual | Current Physical Status |
|||
---|---|---|---|---|---|---|---|---|
Physical Progress (%) |
Description (Date after EOT-2) |
Scheduled Date (After EOT-2) |
Physical Progress (%) |
Revised Date | ||||
Milestone I | 225 Days | 19th September 2020 | 20% | 405 Days | 18th March 2021 | 22.309% | 03-03-2021 | |
Milestone II | 450 Days | 02nd May 2021 | 35% | 630 Days | 29th October 2021 | 35.66% | 09-06-2021 | |
Milestone III | 675 Days | 13th December 2021 | 75% | 855 Days | 11th June 2022 | |||
Scheduled Completion | 912 Days | 07th August 2022 | 100% | 1092 Days | 03rd February 2023 | |||