Salient Features

Salient Features of Project

Project NameFour Laning of Dwarka (Kuranga) – Khambaliya – Devariya Section from Km. 203/500 to 176/500 and from Km. 171/800 to Km. 125/000 (designed length 71.890 km) of NH-151A in the State of Gujarat under Bharatmala Project on Hybrid Annuity Mode (Package - I)
NH No. (New/old)NH-151A (Package-1)
Scheme/PhaseConstruction Development Phase Bharatmala
Mode of the Execution (HAM)Hybrid (Annuity) Mode
No. of Lanes/ConfigurationFour Laning
Length of the Project (in Km)71.820 Km (Existing from 203+500 to 176+500 and Existing from 171800 to 125+000 also SH-25 4.6 Km from 125+000 to 130+000)
Contract Price (in Cr)1101.00 Cr.
Length of Service Road (in Km)2 x 9.090Km
Length of Drain (in Km)32.885 L-Km
No. of ROB01 No (0+527)
No. of Major Bridges04 No Reconstruction
No. of Minor Bridges16 No Reconstruction 04 No Widening & Rehabilitation
No. of Toll Plazas 01 No (61+400)
No. of Vehicular Underpass 06 No New Construction
No. of Box Culvert 24 No Reconstruction 11 No Widening & Rehabilitation
No. of Hume Pipe Culvert69 No New construction 16 No Widening & Rehabilitation
No. of Major Junction Nil
No. of Minor Junction 55 No (T type: 34, X type: 20, Y type: 1)
No. of Bus Bays50 No
Contractor Name (SPV & Parent Company)GR Dwarka Devariya Highway Private Limited (GDDHPL) & G R Infraprojects Ltd.
Date of Award (LOA Date)08th March 2019
Agreement Signing Date 22nd May 2019
Appointed Date08th February 2020
Construction Period (in Days)912 Days
Scheduled Date of Completion07th August 2022
Extension of Time (EOT)180 Days (approved from Authority)
Revised Schedule Date of Completion03rd February 2023
Independent EngineerLEA Associate South Asia Pvt. Ltd (LASA
Operation & Maintenance Period15 Years from the Commercial Operation Date
Independent Engineer Mobilization Date20th November 2019
Independent EngineerLEA Associate South Asia Pvt. Ltd (LASA)
Authority NameNational Highways Authority of India, PIU-Rajkot